Sets the predecessor of a task as another task in the job
Syntax
alter task <task reference> set predecessor task <predecessor task name>
Parameters
task reference
String. Reference to the task to set the predecessor for, consisting of job name, task name, and optionally project name.
predecessor task name
String. Name of the task to set as this task's predecessor.